Source references updated November 26, 2026 · Oath 5.1.2 (112)
Guide source version
Checked against the 5.1.2 source. Older screenshots are illustrative and may show controls absent from this release.
Recovery phrase
Choose Import wallet and enter the original words in order. BIP39, Electrum and aezeed have distinct validation and derivation rules. Electrum and aezeed recover supported Bitcoin accounts, not every asset associated with the original software. Aezeed does not restore Lightning channels.
Additional passphrase
A BIP39 passphrase creates a different wallet. Preserve its exact capitalization and spaces. Electrum seed extensions and aezeed passwords follow their own rules. None of these is interchangeable with the app passcode or iCloud backup password.
Private key
Choose Import private key and the matching network. Ethereum & EVM groups compatible EVM networks; other chains have their own accepted formats. A single key or account-scoped extended key does not recover an entire phrase wallet. Never use an online converter to guess or rewrite private material.
iCloud backup
Restore an eligible .oathbackup file with the password that encrypted it. Keep iCloud Drive available for download. Electrum and aezeed wallets are excluded from iCloud export in this release. The old passkey and nearby-device transfer instructions are not the current flow.
Confirm the result
Compare a known receiving address on the original network. Allow balances and history to refresh. If it differs, stop and check the original format, account path and passphrase before deleting the source wallet or assuming funds are missing.
See the current security model, Help Center, and release verification record. Never share recovery words, private keys or backup passwords with support.